Matix Fertilisers - Project Status
Project Status as on Jan 31, 2012
|
Land - The required land is allocated by WBIDC and possession taken in Panagarh Industrial Park near Durgapur in West Bengal. |
|
Approvals - All key statutory approvals are in place. The Department of Fertilisers, Government of India has recognized the project implementation for subsidy dispensation. |
|
Environmental clearance - Received Environment Clearance as well as consent to establish Fertiliser complex. |
|
Technology - Plant is using latest technology from KBR, USA for Ammonia and Saipem, Italy for Urea. |
|
Engineering - Basic engineering complete. Detailed engineering at 90% model review stage. |
|
Procurement - Procurement of all equipment and packages complete. Several equipment already arrived at Site and erection has started. |
|
Construction - Construction almost 50% complete. |
|
Feedstock - Executed Firm contract for supply of required CBM gas for 20 years. |
|
Financing - Achieved financial closure and started drawdown by consortium for reputed banks led by IDBI. |
|
Organisation - Highly experienced team from industry in place; further recruitment in progress as per schedule. |
Site
Matix Fertilisers & Chemicals Ltd.
Mauza No - Pondali - 77, Ausgram 2, Panchayat Samity, Kota gram, Dist - Burdwan,
West Bengal, India.
Durgapur Office
MNAV 61, Urbashi, North Avenue, Bengal Ambuja Housing Development Ltd.,
City Centre,
Durgapur - 713216, Dist - Burdwan, West Bengal. |
Kolkata Office